EDINBURGH GALLERIES 

7

CALL FOR A QUOTE:

0150 663 7840

 

Edinburgh Galleries

Interserve were awarded the 22million pounds refurbishment project and commenced in late 2018 however the project has already risen in cost and experienced delays. Originally the £22m project was valued at £9m and was set to complete in 2018, but development was put on hold as it underwent a series of redesigns. Construction News’ sister site, The Architects’ Journal, previously reported that a start on site had been delayed in early 2017 due to value engineering in a bid to keep the project to its revised £16.8m budget. Extra design and project costs meant that the overall project cost still rose to £22m.

Work started on site at the end of 2018 and the first phase of the project, which included a new entrance area and retail space, was completed in 2019.

The second phase, which will involve the conversion of 1970s buildings into a suite of galleries, was expected to be completed early next year, but the defects will now push the completion date back to the end of 2021.

National Galleries of Scotland director general John Leighton said: “In the course of this work it has become apparent that there are some unexpected defects within the 1970s building which sits beneath the original 19th century National Gallery. These include issues with damp penetration and inadequate drainage in and around the site.

 

CDS were awarded 3 major specialist’s packages in excess of 1.5million pounds as part of the refurbishment works which included Demolition & Downtakings, Builders work in connection to services and Temporary Support Systems. CDS are still working on the project and have again being able to use the industry’s most advance Remote Demolition Robots to remove vast areas of soft strip, walls and concrete floors in excess of 2m deep along with our specialist cutting techniques to maintain the structural integrity of the existing structures as works progress.  CDS have used our wire sawing and track sawing methods of cutting to great affect as these works progress along with our strong relationship with Maybe we have been able to adequately support areas as concrete is being removed safly.

May I take this opportunity to thank you all for your efforts during the Christmas and New Year shifts.  The works were not easy by any stretch of the imagination, compounded by adverse weather conditions , working away from home and site conditions that were not ideal.  We completed the works as far as we could and handed back both possessions on time without any accidents or incidents which we should be proud of.  We had a couple of high level visits from the client who were content with our efforts and achievements.

Mark Johnson, Senior Project Manager – AMCO Rail

 

 

“James Ramsey’s has been using CDS as their proffered specialist cutting contractors for the past 6 years and would highly recommend their services, as a professional concise contractor whom always maintain high levels of professionalism throughout.”

Gary Shepard, Director, James Ramsey’s

 

“I have been utilising CDS for 10 years now whilst working with BAM construction on several innovative projects, including Cross House Hospital, Blair Dardy Primary School and most recently reemployed their services for the Johnnie Walker Experience in Edinburgh. Their high level of workmanship and attention to detail with regards to health and safety is second to none.”

Kris Moir, Project Manager, BAM Construction

 

Core Drilling Specialists Ltd.

Unit 9,
Inchcross Industrial Estate
Whitburn Rd,
Bathgate
EH48 2HR

Sign Up To Our Mailing List